Site infrastructure in place

Client:                        Berkeley Homes Eastern Counties

Contract value:        £14,000,000.00

The construction of over 700 houses and flats, the associated external works and all associated Infrastructure.

We started on site in May 2013 to complete Phase 1 after the previous contractor went into Administration.

Working towards final phases

Since then we have secured all remaining phases, with phases 2 to 6 completing at the end of November 2016 and 5B & 8B external works towards the end of 2017.

We are currently working on the final two phases, 7 & 8, including all infrastructure to complete the site. All works are programmed to be complete by the end of March 2018.